Quick Link for Time Management
Time Managment 6.1 define activities
Time Management 6.2 sequence activities
Time Managment 6.3 Estimate Activity Resources
Time Management 6.4 Estimate Activity Durations:
Time Management 6.5 Develop Schedule:
Time Management 6.6 Control Schedule:
Duration estimating takes information about project scope
and resources and develops durations so that a schedule can be developed.
Duration estimating has been defined as assessing the number of work periods
needed to complete an activity. Estimates should be:
·
Produced by the people most familiar with the
work (or at least approved by them). This observation refers to the importance
of expert judgment,
·
Progressively elaborated, in other words,
estimates will usually become more accurate as the quality of the input data
improves
·
Adjusted for the effects of “elapsed time”,
(whether or not weekends are treated as work periods). Note: Project management
Software makes it much easier to assess the effect of these elapsed times on a
project schedule.
Duration estimating should also consider the difference
between effort and duration. lf four people work 10 hours each on a task, the
total effort that must be paid for is 40 person-hours. lf those four people are
working simultaneously, i.e., in parallel, the duration to complete the work
will be 10 hours. ln summary, durations are used for scheduling and effort is
used to estimate costs,
Estimate Activity Durations
|
||
Inputs
|
Tools
|
Outputs
|
1. Activity
list
2. Activity
attributes
3. Activity
resource requirements
4. Resource
calendars
5. Project
scope statement
6. Enterprise
environmental factors
7. Organizational
Process assets
|
1. Expert
judgment
2. Analogous
estimating
3. Parametric
estimating
4. Three-Point
estimates
5. Reserve
analysis
|
1. Activity
duration estimates
2. Project
document updates
|
Seven Key inputs for
Estimate Activity Durations:
1. Activity List: Described in Section
6.l.3.l, durations must be estimated for each activity.
2. Activity attributes: Described in
Section 6.1.3.2.
3. Activity Resource Requirements:
Duration estimates are affected by how many resources are assigned to a task
(two people can usually complete a task faster than one person). ln turn,
actual availability of those resources is also a major factor. lf resources
prove to be unavailable, some form of outsourcing may be required. As mentioned
earlier, the relative experience level of the resources may also be a
determinant of the planned duration for a schedule activity.
4. Resource calendars: An output of
resource estimating, the calendar would include the availability and capability
of all required resources (people and equipment).
5. Project scope statement: Any
constraints or assumptions or assumptions from the scope statement that may
affect activity durations. A constraint could be that a key stakeholder has
imposed a strict deadline for completion of initial testing. An assumption
might be that hurricane activity will not disrupt product testing in your sea
coast facility and therefore, you will meet the planned deadline.
6. Enterprise Environment Factors: Environmental
factors that may affect during estimates include:
·
Duration estimating database
·
Productivity metrics
·
Published commercial information
7. Organizational process assets:
Organizational process assets that may affect duration estimates include:
·
Historical information on likely durations
·
Project calendars
·
Schedule methodology
·
Lessons learned
Five key tools for
estimate activity duration:
1. Expert judgment: PMI recommends the use
of expert judgment guided by historical information whenever the combination is
possible. Expert judgment is crucial because of the potential that can affect
durations.
2. Analogous estimating: A form of
top-down estimating, this approach uses the actual durations of previous,
similar activities to estimate the duration of future activities. These
estimates are usually adjustment by experts for differences in complexity, size
and risk. Key points:
·
The technique is usually applied in the early
stages of a project when detailed information is limited and is, therefore,
considered a ballpark guesstimate (WAG).
·
Developing such an estimate is not costly, but
the accuracy is limited.
·
The technique is most reliable when
o
The previous activities are similar in fact and
not just in appearance and
o
The individuals making the estimates have the
needed expertise (for example, expert judgment was the first tool).
3. Parametric Estimating: For some tasks,
duration estimates can be derived from the quantity needed multiplied by the
appropriate productivity rate. For example, if a drawing tasks approximately 10
hours and you need 50 drawings, the estimated during of creating the drawings
would be 500 hours.
4. Three-point estimating: Such estimates
can improve accuracy by considering risk. This technique calculates an expected
average duration from the following three estimates.
·
Optimistic:
The best case scenario as seen by someone familiar with the work.
·
Pessimistic:
The worst case scenario as seen by someone familiar with the work.
·
Most
likely: The most likely scenario as seen by someone familiar with the work.
·
In similar fashion, a well-known technique for
doing the same thing is PERT (Program evaluation and review technique). The
differences among PERT, three-point estimate and CPM (Critical path method)
will be discussed in the next process on schedule development.
5. Reserve analysis: Contingency reserves
(sometimes referred to as time reserve or buffers) are sometimes added to
duration estimates to account for risk or uncertainty. Contingency may be a
percentage of the overall schedule or a fixed number of time periods. If used,
reserve time should be documented along with assumption and other data.
Two key outputs for estimate activity durations:
1. Activity duration estimate: Quantities
assessments of the number of work periods (hours, days and so on) needed to complete
an activity (and by extension, to complete the entire project). PMI recommends
that these estimates should also include a range of possible results. Note: Duration
estimates for different activities are assumed to be statistically independent
(the estimate of one task does not determine or Influence the duration estimate
of a different task.
2. Project document updates: Documents
that may be updated include:
·
Activity attributes
·
Assumption in the duration estimates.
Thanks for sharing, I will bookmark and be back again
ReplyDeleteSoftware Estimation Techniques Training
Those rules moreover attempted to wind up plainly a decent approach to perceive that other individuals online have the indistinguishable enthusiasm like mine to get a handle on incredible arrangement more around this conditionjafza auditors
ReplyDelete