Time Managment 6.3 Estimate Activity Resources


Quick Link for Time Management

Time Managment 6.1 define activities

Time Management 6.2 sequence activities

Time Managment 6.3 Estimate Activity Resources

Time Management 6.4 Estimate Activity Durations:

Time Management 6.5 Develop Schedule:

Time Management 6.6 Control Schedule:

Determining what resources (people, equipment, material and facilities) will be needed, along with the associated quantities and time resource. Resource issues also apply to the cost estimating Process.
Estimate Activity Resources
Inputs
Tools
Outputs
1.       Activity list
2.       Activity attributes
3.       Resource calendars
4.       Enterprise environmental factors
5.       Organizational Process assets
1.       Expert judgment
2.       Alternatives analysis
3.       Published estimating data
4.       Bottom-up estimating
5.       Project management software
1.       Activity resource requirements
2.       Resource breakdown structure (RBS)
3.       Project document updates

Five key inputs for Estimate Activity Resources

1.       Activity list: Resourcing estimates should be done for the associated activities.
2.       Activity Attributes: Activity attributes were developed during activity definition and now provide a primary source of data for estimating the resources required for each activity.
3.       Resource Calendars: An organization’s resource calendar system should provide information such as when a resource is available for a work assignment, experience level of a given resource and skill set for individuals.
4.       Enterprise Environmental Factors: information about the existing resource infrastructure (resource availability and skill sets) would be relevant at this step.
5.       Organizational Process Assets: Organizational Process Assets that would affect the estimation of resources required to support project activities include:
·         Staffing policies
·         Procedures for renting or purchasing supplies and equipment
·         Historical information about resource usage on similar projects

Five Key Tools for Estimate Activity Resources:


1.       Expert Judgment: Appropriate subject matter experts will help judge the accuracy of resource estimates.
2.       Alternatives Analysis: This analysis considers the various options for doing the work and assures that appropriate resource estimates are available. For example, a project might pursue either of two technological possibilities or there may be a choice between manual and automated tools/processes, and so on.
3.       Published Estimating Data: Some industries and trade groups collect and publish cost, schedule, and resource data for specific types of work.
4.       Bottom-up Estimating: lf a schedule activity cannot be estimated with reasonable confidence; the work may be decomposed to a lower level to provide more detail. The bottom-up approach then aggregates these estimates at higher levels.
5.       Project Management Software: Most project management software is quite good at organizing resource data for individual team members or groups (sometimes called resource pools). The software can usually define:
·         Resource availability
·         Resource rates
·         Resource calendars
·         Resource breakdown structures (RBS)

Three Key Outputs for Estimate Activity Resources:


1.       Activity Resource Requirements: identifies the type and quantity of resources needed to support each individual schedule activity. lf the work was decomposed below the work package (schedule activity), the resource requirements are added (aggregated) to determine total resource needs for the work package. Estimates should include:
·         The basis of the estimate (method used)
·         Any assumptions that were made
·         Resource availability
·         Resource quantity
2.       Resource Breakdown structure: whereas the WBS focuses primarily on activities, the RBS is a hierarchical structure focusing primarily on resources. The RBS identifies activities to which the resources are assigned as well as the associated time frames. The RBS is also useful in determining whether a resource is available in any given time period.
3.       Project Document updates: Project documents that might be updated include:
·         Activity list
·         Activity attributes
·         Resource calendars