Quick Link for Time Management
Time Managment 6.1 define activities
Time Management 6.2 sequence activities
Time Managment 6.3 Estimate Activity Resources
Time Management 6.4 Estimate Activity Durations:
Time Management 6.5 Develop Schedule:
Time Management 6.6 Control Schedule:
Schedule change control is concerned with the usual factors:
·
Determining the current status of the schedule
·
Influencing the factors that create schedule
changes
·
Determining (and tracking) that schedule changes
have occurred
·
Managing the changes as they occur
Control Schedule
|
||
Inputs
|
Tools
|
Outputs
|
·
Project management plan
·
Project schedule
·
Work performance information
·
Organizational process assets
|
·
Performance reviews
·
Variance analysis
·
Project management software
·
Resource leveling
·
What-if scenario analysis
·
Adjusting leads and lags
·
Schedule compression
·
Scheduling tool
|
·
Work performance measurements
·
OPA updates
·
Change requests
·
Project management plan updates
·
Project document updates
|
Four Key inputs for control schedule:
1. Project Management plan: As described
earlier, the project management plan contains the schedule management plan and
the schedule baseline. The schedule management plan establishes how the
schedule will be managed and how changes will be processed. The baseline is
compared to actual outcomes to determine if preventive actions, corrective
actions, or changes are needed.
2. Project schedule: The most recent,
approved project schedule is the baseline. It is this baseline that will change
if schedule changes are approved.
3. Work Performance information: Provides
information on whether planned dates have been met- Performance reports also
alert the team to issues that may cause future schedule problems. These
problems may potentially read to change requests.
4. Organizational Process Assets:
organizational process Assets that may affect schedule control include:
·
Formal and informer policies regarding
scheduling control (changes, preventive action, corrective action, and
monitoring actual results)
·
Schedule control tools
·
Monitoring and reporting methods
Eight key tools for control schedule:
1. Performance reviews: Includes
information such as actual start and finish dates as well as remaining duration
for partially completed activities. If earned value is used, a method for
measuring “in-progress” activities must be adopted (e.g., percent complete or
the 50-50 rule). The details of earned value will be covered in the cist
management chapter. An important part of schedule control id to determine
whether schedule variations are sufficient to devise responses such as
corrective actions.
2. Variance analysis: Used to assess the
magnitude of schedule variations against the planned baseline. Variance is
defined plan minus actual. Negative variances indicate that work took longer
than expected. For example, if a task was supposed to take five days and
actually took eight days, the variance is negative three days. Variances
outside acceptable boundaries or thresholds may require corrective action.
3. Project management software: Provides
the means to track planned versus actual dates and to forecast expected future
performance.
4. Resource leveling: Uses to optimize the
distribution of work against the available resources (section 6.5.2.4).
5. What-If scenario analysis: Uses
simulation to analyze various scenarios and determine the probability of
different schedule outcomes (section 6.5.2.5).
6. Adjusting leads and legs: used to
refine the schedule by delaying or accelerating work (6.5.2.6).
7. Schedule compression: techniques such
as crashing and fast tracking to reduce the current schedule (6.5.2.7).
8. Schedule tool: The schedule data are
updated to reflect actual progress. Manual or automated scheduling methods are
used to produce an updated schedule.
Five key outputs for
control schedule:
1. Work performance measurements: For
schedule purposes, the schedule variance and the schedule performance index
should be calculated and reported to appropriate stakeholders.
2. Organizational process assets updates:
Organizational process assets that may be updated as a result of schedule
control include:
·
The causes of variances that have occurred
·
Corrective actions chosen and the rationale
·
Other lessons learned with respect to schedule
control
3. Change requests: If change requests
occur during analysis of schedule variances, they should be processed using
integrated change control.
4. Project management plan updates:
Updates to the project management plan may include:
·
Schedule baseline (in response to approved
change request)
·
Schedule management plan (changes in the way the
schedule is to be managed)
·
Cost baseline (additional costs incurred in
compressing the schedule)
5. Project document updates: Documents
that may be updated include:
·
Schedule data (new network diagrams may be
developed to show remaining duration and/or modifications to the original
plan).
·
Project schedule (an updated schedule that
reflects approved changes).
No comments:
Post a Comment