Quick Link for Time Management
Time Managment 6.1 define activities
Time Management 6.2 sequence activities
Time Managment 6.3 Estimate Activity Resources
Time Management 6.4 Estimate Activity Durations:
Time Management 6.5 Develop Schedule:
Time Management 6.6 Control Schedule:
Activities sequencing involves
identifying and documenting interactivity dependencies (also called logical
relationships). The process can be done manually, with software or with a
combination of both. Expert for the
first and last, all activities must have a
predecessor and a successor.
Sequence
Activities
|
||
Inputs
|
Tools
|
Outputs
|
1.
Activity list
2.
Activity attributes
3.
Milestone list
4.
Project scope statement
5.
Organization process
assets |
1.
Precedence diagramming
method
2.
Dependency
determination
3.
Applying leads and lags
4.
Schedule network
templates |
1.
Project schedule network diagrams
2.
Project document
updates |
Five key inputs for sequence activities:
1. Activity list: An output of the
previous process, section 6.1.3.1.
2. Activity attributes: An output of the
previous process, section 6.1.3.2. This information includes predecessors and
successors for each activity.
3. Milestone list: scheduled dates (in the
form of constraints) may exist for milestone, which were described in section
6.1.3.3.
4. Project scope statement: includes
product charismatics that help planned understand required activity sequences.
For instance, there may be physical or technical aspects of the work that make
a mandatory dependency necessary.
5. Organization process assets: the
specific organizational process assets that may affect sequencing project
activities include :
·
Files from the knowledge base on scheduling.
Four key tools for sequence activities:
1. Precedence diagramming method: This is
one way to display a schedule in network fashion; it is also called
activity-on-node. It was developed in the early 1960sat Stanford University and
is the method that project management software uses today. The activities are
listed inside boxes (called nodes) and are connected by lines (or arrows) to
indicate sequences.
Design
|
Test
|
Produce
|
The PDM approach uses the
following four types of dependencies:
·
Finished-to-start:
Initiation of the successor activity depends on completion of the predecessor
activity.
·
Finished-to-finished:
Completion of the successor activity depends on completion of the
predecessor activity.
·
Start-to-start:
Initiation of the successor activity depends on completion of the predecessor
activity.
·
Start-to-start:
Completion of the successor activity depends on completion of the
predecessor activity.
PDMs offer several advantages
over other methods (such as arrow diagrams):
·
The technique provides flexibility in sequencing
activities by allowing four types of logical dependencies. By comparison, arrow
diagrams are limited to finish-to-start dependencies.
·
The technique does not require the use of
“dummy” activities whenever multiple dependencies are needed in a schedule.
·
Finally, the technique adds the concept of leg
and lead times between activities.
2. Dependency determination: The following
three types of dependencies are used during activity sequencing:
·
Mandatory
dependencies: Also referred to as “hard logic,” mandatory dependencies are
inherent in the nature of technical limitations of some kind. For example, you
cannot shingle the roof of a builder until the roof has been build.
·
Discretionary
dependencies: Known as “soft logic” or “preferential logic” these optional
dependencies are usually chosen because they represent “best practice” or there
is a preferred approach even though other approaches also are acceptable.
·
External
dependencies: these dependencies usually involve interfaces outside the
project. Examples include waiting on delivery of hardware form an outside
source or waiting on delivery of aircraft engines before installation in the
airframe.
3. Applying leads and lags: Adjustment of
lead and lags times may help define the timing of the work more accurately. A
lead time allows the successor (follow-on) task to be accelerated. Conversely,
a lag time delays the successor activity.
4. Schedule network templates: using
networks from a similar project as a guide. Templates may address an entire
project or only portions.
Two Key out puts for Sequence Activities:
1. Project Schedule Network Diagrams: A
schematic display of the project activities and their logical relationships,
most often using PDM as the method of display.
2. Project Document Updates: As a result
of sequencing, the following documents could be updated:
·
Activity lists
·
Activity attributes
·
Risk register
Start-to-Start (SS) is a kind of dependency shows that two activities determine to start together.
ReplyDeleteFinish-to-Finish (FF) in a project illustrates that two activities in a project determine to finish together.