1. Cost Management 7.1 Estimate costs
2. Cost Management 7.2 Determine Budget
Cost control is part of integrated change control. Effective cost control requires management of the approved cost performance baseline (often simply called the cost baseline or approved budget) and any changes to that baseline. Cost control includes the following:
·
Influencing the factors which create changes
·
Ensuring that change requests are acted on in a
timely manner
·
Managing the change Process
·
Keeping costs within authorized funding
·
Detecting and understanding cost variances
·
Recording all changes
·
Preventing inappropriate changes
·
Informing stakeholders of changes
- Bringing expected cost overruns within
acceptable limits
Control Costs
|
||
Inputs
|
Tools
|
Inputs
|
1. Project
management Plan
2. Project
funding requirements
3. Work
performance information
4. Organizational
Process assets
|
2. Forecasting
3. To-complete
Performance index
4. Performance
reviews
5. Variance
analysis
6. Project
management software
|
1. Work
performance measurements
2. Budget
forecasts
3. OPA
updates
4. Change
requests
5. Project
management Plan updates
6. Project
document updates
|
Four Key inputs for Control Costs:
1. Project Management Plan: Contains the
following information used to control costs:
·
Cost
performance baseline: The baseline (plan) is compared with actual results
to determine if changes, preventive actions, or corrective actions are
necessary.
·
Cost
management plan: Describes how project costs are to be managed and
controlled.
2. Project Funding Requirements: Described
previously in this site, Section 7.2.3.2.
3. Work performance information: Includes
the following status information:
· Deliverable completed or partially completed
·
Costs authorized vs. costs incurred (plan vs.
actual)
·
Estimates for completing the work (forecasts)
·
Percent physically complete for work in progress
4. Organizational Process Assets: The
following organizational process assets may affect cost control:
·
Formal and informal cost control procedures and
guidelines
·
Cost control tools
·
Monitoring and reporting methods
Six Key Tools for Control Costs:
1. Earned Value Management: Earned value
is a method of performance measurement that provides current cost and schedule
status at regular intervals. This site describes earned value as it relates to
current status (Tool #2, forecasting, will address the forecasting portion of
the technique). See course slides #98 through#120 for coverage of what you must
know for the exam.
2. Forecasting: Work performance
information through each successive reporting period is used to predict future
performance on the project, in this site and course slides referenced above.
3. To-Complete Performance index:
Calculates the cost performance (CPl) that must be maintained to achieve a
performance goal. Usually the preference is to maintain the original budget
(finish at the BAC) or in some cases performance may have deteriorated to the
point that the current EAC becomes an acceptable goal. The course slides
referenced above show examples.
4. Performance Reviews: Regular meetings
to review and assess cost performance information. One or more of the following
techniques are normally employed:
·
Variance
analysis: Planned versus actual performance in the areas of cost and
schedule.
·
Trend
analysis: Examining performance over time and projecting to the future to
determine whether performance is improving, remaining the same, or
deteriorating-
·
Earned
value: A special technique that accomplishes both variance analysis as well
as trend analysis (CPl, SPI).
5. Variance Analysis: Variance analysis
determines the magnitude of cost variances and then determines whether
corrective or preventive actions are needed. In many organizations, acceptable
thresholds are established to decide whether a variance is minor or major. The
range of acceptable variance usually grows more narrow as a project nears
completion.
6. Project Management Software: Automates
the analysis of data by tracking the values for PV, EV, and AC.
Six Key Outputs for Control Costs:
1. Work Performance Measurements: This involves
the actual documentation and communication of calculated measurements such as
CV, SV, and CPR. This information is documented and communicated to appropriate
stakeholders.
2. Budget Forecasts: calculations such as
EAC should be recorded and communicated to stakeholders.
3. Organizational Process Assets Updates:
organizational process Assets that may be updated as a result of cost control
include:
·
Causes of variances
·
Corrective actions chosen and the reasons
·
Other lessons learned as a result of cost
control
4. Change Requests: Change requests may
lead to changes in the budget (increase or decrease) and, as usual, change
requests must be processed using integrated change control.
5. Project Management plan updates:
components of the project management plan that may be updated as a result of
cost control include:
·
Cost
performance baseline: The baseline (plan) is compared with actual results
to determine if changes, preventive actions or corrective actions are
necessary. In some cases, cost variances are so severe that the baseline must
be extensively revised to produce a realistic budget.
·
Cost
management plan: Describes how project costs are to be managed and
controlled
6. Project Document updates: Documents
that may be updated include:
·
Cost estimates
·
Basic of estimates
Nice info. The four new processes added to existing Knowledge Areas and the addition of a new, 10th Knowledge Area will definitely impact the make-up of the PMP and CAPM PMI certification exams. To get yourself prepared for PMP http://www.pmstudy.com is good one.
ReplyDelete