1. Cost Management 7.1 Estimate costs
2. Cost Management 7.2 Determine Budget
Cost budgeting involves aggregating estimated cost estimates
for all individual activities or work packages so that a cost baseline can be
established for measuring performance. The baseline includes authorized budgets
and contingency reserves, but excludes management reserves (the extra amount
for "unknown unknowns").
Determine Budget
|
||
Inputs
|
Tools
|
Outputs
|
1. Activity
cost estimates
2. Basis
of estimates
3. Scope
baseline
4. Project
schedule
5. Resource
calendars
6. Contracts
7. Organizational
process assets
|
1. Cost
aggregation
2. Reserve
analysis
3. Expert
judgment
4. Historical
relationships
5. Funding
limit reconciliation
|
1. Cost
performance baseline
2. Project
funding requirements
3. Project
document updates
|
Seven Key inputs for Determine Budget:
1. Activity Cost Estimates: Cost estimates
for each activity within a work package are aggregated so that the cost of each
individual work package is known. Work package estimates can then be aggregated
at the control account level and so on.
2. Basis of Estimates: Described in this
side (includes scope, deliverables, how the estimate was created, assumptions,
constraints, and an estimated range of possible outcomes). This information
should also address whether indirect costs are included in the budget.
3. Scope Baseline: The following three
items form the scope baseline and contain information that is relevant to
establishing the cost baseline.
·
Scope
statement: The scope statement is relevant to budgeting if it identifies
any constraints on the expenditure of money (such as a fiscal year that
constrains when certain funds can be spent).
·
WBS:
Provides a structure to organize the cost estimates into useful categories
(cost accounts or control accounts).
·
WBS
dictionary: Provides the detailed information of what is needed to produce
the deliverables for each work package.
4. Project Schedule: The schedule must be
known to establish when specific costs will be incurred.
5. Resource Calendars: The availability of
resources affects both the cost as well as the timing of the work. This was
considered previously in this site, paragraph 6.3.3.4.
6. Contracts: Provides information on
costs incurred through outsourcing of portions of the work.
7. Organizational Process Assets: The
following organizational process assets may affect cost budgeting:
·
Formal and informal cost budgeting procedures
and guidelines
·
Cost budgeting tools
·
Reporting methods
Five Key Tools for Determine Budget:
1. Cost Aggregation: Described previously.
Cost estimates are established for work packages and summarized at higher
levels such as control accounts or the project total.
2. Reserve Analysis: Also discussed under
cost estimating, the course slides will show an example of how reserve analysis
relates to the cost baseline (at the first output below, cost performance
baseline).
3. Expert Judgment: The use of appropriate
subject matter experts to improve the accuracy of the budget.
4. Historical Relationships: Described
previously for duration estimating, this technique, formerly called parametric
estimating (the use of mathematical correlations), is also used for cost
estimating and budgeting. As before, parametric models are most accurate when:
a.
The historical information used to develop the
information was accurate
b.
The parameters in the model are readily
quantifiable
c.
The model is scalable (works well for small as
well as large projects)
5. Funding Limit Reconciliation: Some
organizations "reconcile" funding expenditures to prevent large
fluctuations in disbursements. In some cases, this process relies on tinkering
with the timing of certain activities through the use of imposed date
constraints.
Three Key Outputs for Determine Budget:
1. Cost performance Baseline: The cost
baseline is a time-phased budget used to measure and monitor cost performance.
The baseline is developed by summing estimated costs by time period and
displaying them (often in the form of an S-curve). Large projects may have
multiple cost baselines. See Figure 7-6 on this site and Course Slides #94
through #97 for examples of an S-curve and the use of reserve.
2. Project Funding Requirements: As
mentioned above, funding is not always a smooth, continuous process. The
availability of the funds usually occurs in increments and disbursements may
not automatically be spread evenly. Many organizations attempt to smooth the
process as much as possible.
3. Project Document Updates: Documents
that may be updated include:
·
Risk register
·
Cost estimates
·
Project schedule
No comments:
Post a Comment