1. Cost Management 7.1 Estimate costs
2. Cost Management 7.2 Determine Budget
Cost estimating involves developing
an estimate of the costs of all resources needed to complete the project. The
resources that need to be estimated include labor, equipment, materials,
facilities, services and any special categories such as contingency or an
allowance for anticipated inflation.
The accuracy of estimates tends to
improve as a project moves though its life cycle. For instance, an estimate
during the initiating phase (known as a ROM or rough order of magnitude) may
have a range of accuracy of -50% to +50%. Other ranges of accuracy that are
used in some industries and have been tested in the past include:
·
Order of
magnitude estimates: “Ballpark” estimates without detailed data, for
example, analogous estimates. This estimate is similar to ROM mentioned in the
previous paragraph. The range of accuracy is given as -25 to +75% and would be
used for initiating or project approval.
·
Budget
estimates: Based on slightly better data and used to establish initial
funding during the early stages of planning. The range of accuracy is given as
-10 to +25%.
·
Definitive
estimates: Prepared dorm well defined, detailed data. A bottom-up estimate
using estimates of WBS work packages is a common example of this kind of
estimate. This estimate would be done in the latter stages of planning and be
used to establish a cost baseline. Range of accuracy is -5 to +10%.
Finally, cost estimating
potentially includes evaluating trade-offs among alternatives such as spending
more money in the design phase to save money during production or operations.
Estimate Costs
|
||
Inputs
|
Tools
|
outputs
|
1. Scope
baseline
2. Project
schedule
3. Human
resource plan
4. Risk
register
5. Enterprise
environmental factors
6. Organizational
process assets
|
1. Expert
judgment
2. Analogous
estimating
3. Parametric
estimating
4. Bottom-up
estimating
5. Three-point
estimating
6. Reserve
analysis
7. Cost
of quality
8. Project
management estimating software
9. Vendor
bid analysis
|
1. Activity
cost estimates
2. Basis
of estimates
3. Project
document updates
|
Six key inputs for estimate costs:
1. Scope baseline: The following three
items form the scope baseline and contain information that is necessary for
accurate cost estimating.
·
Scope
statement: contains the product description, key deliverables, constraints
and assumptions. For cost estimating, a decision must be made as to whether the
estimates will include only direct costs or will also include indirect costs.
·
WBS: Provides
a structure to organize the cost estimates into useful categories (cost
accounts or control accounts).
·
WBS
dictionary: Provides the detailed information of what is needed to produce
the deliverables for each work package.
2. Project schedule: cost estimates are
closely related to what resources will be used and for how long (activity
durations).
3. Human resource plan: Cost estimates may
be affected by personnel rates and any associated rewards programs. The HR plan
also contains the resource calendar with a staffing plan. This plan provides
estimated time frames for various resources.
4. Risk register: The risk register should be reviewed so
that projected risk mitigation costs may be included in the cost estimates.
5. Enterprise environment factors: For
cost estimating purposes, environmental factors would include marketplace for
any conditions (what products are actually available in the marketplace for any
portions of the project that may be outsourced) and any commercial databases
that contain cost estimating.
6. Organizational process assets: The
following organizational processes, policies, procedures and knowledge bases may
affect cost estimating:
·
Cost estimating policies and templates.
·
Historical information about similar products
that may help define cost estimates.
·
Lessons learned: This would include cost
information from similar projects.
Nine key tools for estimate costs:
1. Expert judgment: Expert judgment,
guided by historical information on similar project, is used to improve the
accuracy of available estimating data. Expert judgment may also assist in
choosing the most appropriate estimating method.
2. Analogous estimating: Previously
described as one of the tools for duration estimating, the technique is also
used for estimating costs. Key points are:
·
Uses the actual costs from a similar project and
adjusts the estimate according to whether the current project is expected to be
harder or easier than the previous one.
·
Also called top-down estimating.
·
Done early in the project life cycle in most
cases.
·
It is a form of expert judgment.
·
Less costly than other techniques but also less
accurate.
·
Most reliable when:
o
The previous projects were similar in fact and
not just in appearance.
o
The estimators have the needed expertise.
3. Parametric estimating: mathematical
modeling for the purpose of predicting project costs the models seek factors
that are highly correlated, for example, dollars per square foot of living
space in residential construction. Parametric models are most reliable when:
·
The historical information used to develop the
information was accurate.
·
The parameters in the model are readily
quantifiable.
·
The model is scalable (works well for small as
well as large projects).
4. Bottom-up estimating: Estimating the
cost of individual work items and then “rolling up” or summarizing the
estimates to get a project total. The most widely accepted technique uses the
work packages as the “individual items”. As the items estimated get smaller,
the estimates usually become more accurate but also more costly to develop.
5. Three-point estimates: Used exactly in
the same way that it was for duration estimates. Three-point or PERT estimates
are useful when there is underlying uncertainty in the work. As before,
optimistic, most likely and pessimistic estimates are used to calculate an
average cost that considers the range of uncertainty in the estimates. The
formulas are the same except that the estimates are for costs rather than
durations.
6.
Reserve
analysis: Cost estimates must consider potential risks in the estimates for
individual activities. Extra money can be incorporated into the pan in several
ways:
·
Place the money into the budget for an
individual work package that is considered risky. This approach is for handling
“known unknown,” is referred to as contingency reserve and the money is already
in the cost baseline.
·
Place the money in a zero duration (fictitious)
activity that is placed at the end of a path for a group of activities. Such
activities can be placed at multiple points in the schedule as the planners
feel is prudent.
·
Finally, the money may be a separately planned
quantity that is not associated with specific work package. This approach is
for handling “unknown unknowns,” i.g., situations that are difficult to
predict. This amount of money id known as management reserve, is often a
percentage of the estimated cost and is not the currently approved cost
baseline.
The use of either type of reserve
is intended to reduce the chance of a cost overrun and the topic is discussed
further in the chapter on risk management.
7. Cost of quantity: the cost of quality
includes activities such as training and audits that are done as part of
quality management (which will be covered in more detail in the chapter on
quality).
8. Project management estimates software: Facilitates
rapid consideration of the cost estimates for various project scenarios.
9. Vendor bid analysis: Applies to
outsourced work using procurement management processes.
Two key outputs for estimate costs:
1. Activity cost estimates: Quantitative
assessments (usually expressed in units of currency) of the like costs of the
resource needed to complete the project. Cost estimates may be improved though
refinements during the project life cycle. Cost estimates should consider risks
and should address the following areas: labor, materials, supplies and
services, facilities, information technology and special categories such as
inflation and cost reserve.
2. Basic of estimates: Should include the
following information:
·
Description of the work (usually WBS)
·
Basis of the estimate (how it was developed)
·
Assumptions and constraints
·
A range of possible results
·
Confident level (related to the range, i.e., a
wide range indicates less confidence in the probability of a given outcome)
3. Project document updates: documents
that may be updated as a result of cost estimating include the risk register.
My cousin recommended this blog and she was totally right keep up the fantastic work!
ReplyDeleteSoftware Estimation Techniques
Hey, If you want to Boost your career then you should check this out - The PMP® Program Will Skyrocket Your Career : Course Review
ReplyDeleteThe PMP course provides managers with the latest information on Project Management norms and practices-VISIT OUR WEBSITE
ReplyDeletepmp Certification