1. Which of the following is not a
type of network logic used in establishing activity dependencies?
a)
Critical logic
b)
Hard logic
c)
Preferential logic
d)
External logic
2. Your team has agreed on the preferred activity sequences for your South Entrance Security program. Durations have been estimated and resource availability to support the schedule has been verified. In displaying the resulting schedule, ____________would generally illustrate______________ better than network diagrams.
a)
Milestone charts; activity sequencing
b)
Milestone charts; the critical path
c)
Bar charts; resource trade-offs
d)
Bar charts; Progress or status
3. Fast tracking involves:
a)
Developing workarounds for problems that have
occurred in the past
b)
An increase in schedule risk
c)
Meeting schedule objectives by doing the job
right the first time
d)
Reducing delays through better allocation of
resources
4. A team member just informed you that resource availability was just reduced across the entire organization. Unfortunately, you now have more tasks scheduled for next week than thL resources available can possibly handle. One possible solution for this predicament is to employ ldeally, this technique would be limited to activities:
a)
Resource leveling; with positive float
b)
Resource leveling; on the critical path
c)
Crashing; with negative float
d)
Crashing; with zero float
5. If you expect an activity to take three days and it takes two days, the variance is:
a)
+5 days
b)
+1 day
c)
-1 day
d)
-5 days
6. Tasks A, B, and C have
durations of 12 days each and are performed in sequence using finish-to-start
dependencies. Task D has duration of 10 days and a finish-to- finish dependency
with Task A. What is the late finish for Task A and Task D?
a)
Task A= 36 and Task D = 36
b)
Task A= 12 and Task D = 12
c)
Task A= 36 and Task D = 12
d)
Task A= 12 and Task D = 36
7. You have been a project manager for more than twenty years and have noticed that schedule changes tend to increase project costs. As a result of your experience and recent project management certification, you know that work performance information and the project scfredule are inputs to controlling the schedule. Which of the following is not a tool for Control Schedule?
a)
Change requests
b)
Resource leveling
c)
Variance analysis
d)
Performance reviews
8. Which of the following describes an approach to crashing the project?
a)
Achieving planned duration by doing the job
right the first time
b)
Achieving planned duration by getting more
cooperation from the stakeholders
c)
Reducing project duration by appropriate use of
overtime
d)
Reducing project duration by doing more work in
parallel
9. Scheduling heuristics are:
a)
Optimal solutions
b)
Shortest possible durations
c)
Methods for doing more work in parallel
d)
Rules of thumb
10. The major difference between a milestone and an activity is that milestones:
a)
Have zero duration
b)
Have zero float
c)
Can only be delayed with proper approval
d)
Are identified by customers
11. The objective of fast tracking a project is to:
a)
Add resources to critical activities
b)
Reduce the Project duration
c)
Reduce the number of resources needed by the
project
d)
Provide faster status reporting
12. You are kicking off a complex project that seems to have numerous loops and conditional branches. A more experienced colleague recommended a technique that is not used as much as traditional network diagrams but is capable of dealing with your situation. Which of the following did she recommend?
a)
PERT
b)
GERT
c)
DERT
d)
QWERT
13. If an activity lies on the critical path, its total float will normally be:
a)
Greater than its free float
b)
Positive
c)
Zero
d)
Negative
14. Precedence diagrams are often preferred over arrow diagrams because they:
a)
Handle a large number of activities better
b)
Simplify scheduling by avoiding overlapping
activities
c)
Do not require dummy activities
d)
Allow the project manager to identify the
critical path
15. Which of the following items best identifies all the tasks that must be included in the schedule?
a)
The master schedule
b)
The WBS
c)
The technical baseline
d)
The network diagram
16. The schedule baseline:
a)
Is less important than the scope baseline
b)
Does not consider resource availability
c)
Can only be determined accurately with computer
analysis
d)
Is used to measure project schedule performance
17. Which of the following is a distinguishing characteristic of projects?
a)
They are ongoing in nature
b)
They put scheduling techniques into active use
c)
They are temporary
d)
Time, cost, and quality are integrated for
planning
18. Which of the following statements about float (slack) is true?
a)
The project manager may use float as a guide in
making resource assignments
b)
The project manager should generally use
available float as early in the project as possible
c)
Negative float is not of concern if enough
activities have positive float
d)
Negative float can often be reduced by slowing
the project expenditure rate
19. In a network logic diagram, the critical path is the:
a)
Path that contains the most important activities
b)
Most expensive path through the network
c)
Shortest path through the network
d)
Longest path through the network
20. __________Is an indication of
scheduling flexibility.
a)
Early staff
b)
Late start
c)
Slack
d)
Near-critical Path
21. Activity definition is an
essential first step in building an accurate project schedule. lf the activity
list is inaccurate, then the schedule will also be inaccurate. Which of the
following is an output of defining activities?
a)
Milestone list
b)
Decomposition
c)
Activity list updates
d)
Activity dependencies
22. In the arrow diagramming
method, ________ is a constraint that does not require an expenditure of
resources.
a)
A logical dependency
b)
A dummy activity
c)
A successor
d)
The critical Path
23. Your project to update the
security system for a major bank involves work that is uncertain and difficult
to estimate. You have decided to try using PERT to get a better idea of the
range of possible durations for this work. Accordingly, you have asked several
expert to come up with three estimates (best case, worst case, and most likely.
The estimates they provided were 7 days, 19 days, and 10 days
respectively-Using PERT, what is the expected average duration for this work?
a)
10 days
b)
11 days
c)
12 days
d)
PERT is not used for this type of estimating
24. There are organizations that
have performed studies of how long it "should take" to perform
certain activities. The information is often useful in estimating activity durations-
This technique is known as - and is a -of estimate activity resources.
a)
Work analysis; tool
b)
Work analysis; output
c)
Published estimating data; tool
d)
Published estimating data; output
25. Which of the following
dependency descriptions is incorrect?
a)
Finish-to-start: initiation of the successor
depends on completion of the predecessor
b)
Finish-to-finish: Completion of the successor
depends on completion of the predecessor
c)
Start-to-start: initiation of the successor
depends on initiation of the predecessor
d)
Start-to-finish: initiation of the predecessor
depends on completion of the successor
26. Resource leveling will
generally:
a)
Require more resources in the long run
b)
Delay the end date of the Project
c)
Reduce total costs for the Project
d)
Have no effect on schedule
27. Your experience and training
have taught you that identifying the critical path is crucial for establishing
accurate expectations about schedule outcomes. Which is the least correct
statement about the critical path?
a)
The critical path is the shortest time in which
the project can be completed.
b)
The critical path is the longest path.
c)
The critical path has the least float.
d)
The critical path has zero float.
28. The project activity list
should generally:
a)
Be organized by WBS element
b)
Include only those activities on the critical
path
c)
Include only those activities with confirmed
resource assignments
d)
Include only those activities with confirmed
start dates
29. If the end date of an initial
plan is later than the desired date, which of the following should generally be
tried first?
a)
Start non-critical path activities at their
early start dates
b)
Examine the activity sequences to determine
whether more work can be done in parallel
c)
Add more resources to critical path activities
d)
Negotiate a reduced scope for any activities
with negative float
30. If the expected duration of
most project activities is represented by a triangular distribution skewed to
the left, the project duration calculated using PERT will irost likely be:
a)
More pessimistic than CPM and more optimistic
than Monte Carlo simulation
b)
More optimistic than CPM and more pessimistic
than Monte Carlo simulation
c)
More pessimistic than either CPM or Monte Carlo
simulation
d)
More optimistic than either CPM or Monte Carlo
simulation
31. The roof must be built before
the roof can be shingled is an example of a/an:
a)
External dependency
b)
Internal dependency
c)
Mandatory dependency
d)
Discretionary dependency
32. Lag time is:
a)
Derived from a forward and backward pass
b)
Waiting time
c)
The time a task can be delayed without delaying
the project completion
d)
The time a task can be delayed without delaying
the successor task
33. Which project management tool
would show the critical path?
a)
WBS
b)
Project charter
c)
Milestone chart
d)
Network diagram
34. Your most recent project
management training class suggested that project managers increase their
attention to the use of float. Which of the following statements about free
float is correct? Free float ______________.
a)
Identifies resources assignment to the project
that are not actively working on project tasks
b)
Identifies how long a task can be delayed
causing a delay in the project
c)
Identifies how long a task can be delayed
without causing a delay in the start time of the immediate successor
d)
Identifies how much time it will take to
complete the remaining work on the project
35. Given the data provided below,
which activity should be crashed to reduce the project duration by one day? All
times are in days.
Task
|
Predecessor
|
Normal
time
|
Crash
time
|
Crash
cost per day
|
Start
|
-
|
-
|
-
|
-
|
A
|
Start
|
4
|
4
|
N/A
|
B
|
A
|
5
|
3
|
$20
|
C
|
Start
|
4
|
2
|
$50
|
D
|
C
|
6
|
4
|
$35
|
End
|
B,D
|
-
|
-
|
-
|
a)
A
b)
B
c)
C
d)
D
36. If you are more constrained by
resource availability than by cost or schedule, you might:
a)
Employ the concept of crashing to conserve
resource
b)
Employ resource leveling to make the best use of
scarce resource
c)
Use Monte Carlo simulation
d)
Use fast tracking to conserve resources
37. A project with multiple
critical paths:
a)
Will need more resources than usual
b)
Is more risky
c)
Is not possible (there is only one critical
path)
d)
Must be analyzed using computerized tools
38. How does standard deviation
relate to risk?
a)
Standard deviation indicates how unsure the
estimate is.
b)
Standard deviation indicates the extent of
management reserve.
c)
Standard deviation has no bearing on risk.
d)
Standard deviation calculates additional
resources needed during crashing.
39. You are a project manager
currently assigned to the Upper Fiji Campaign to Save the Whales. You are
developing a public relations program and have asked for schedule estimates
from your able assistant Dorothy Dash, PMP@. She reports that the uncertainty
in the work makes the use of PERT a good idea. Therefore, she gives you the
following three estimates: the optimistic estimate for completing the program
is 18 weeks, the most likely estimate is 21 weeks, and pessimistic estimate is
42 weeks. Using PERT, what is the probability that the work will be completed
within a range from 20 weeks to 28 weeks?
a)
5o%
b)
68.3%
c)
95.5%
d)
99.7%
Use the following information to answer questions 40-42.
You have been hired by the Young
Republicans Committee to convince moderate Democrats in your great state of New
Yorkshire to vote for their Republican candidate. You are personally indifferent about
politicians, but the Republicans are paying well at the moment and your car
needs new tires and a muffler. The first part of the project as you have
conceived it consists of four major tasks and you have collected the following
information: Task A can finish on day 4 and cannot finish later than day 5 or
the project will be delayed (and the evil-doer Democrat candidate may be
elected and you will never be hired again). Task B can be completed by day 8
and must also be completed by day 8 or you will be late (and you know what that
means)! Task C can be completed on day 12 and
must be completed by day 15 or the Project may be late. Finally, Task D can be
completed by day 20 but must be completed by day 15 or the project will be
late.
40. Which task has the most float?
a)
Task A
b)
Task B
c)
Task C
d)
Task D
41. Which task has the least
float?
a)
Task A
b)
Task B
c)
Task C
d)
Task D
42. Which task most threatens
completing the project on time?
a)
Task A
b)
Task B
c)
Task C
d)
Task D
43. Which of the following terms
is not associated with a precedence diagram?
a)
Critical Path
b)
Slack
c)
Dummy task
d)
Lag
44. The default display in many
project management software programs is the Gantt chart, which is also called a
bar chart. A distinctive advantage of the Gantt chart is that it _________.
a)
Clearly shows any schedule variances
b)
Is the best to view the critical path
c)
Identifies dummy tasks
d)
Is the preferred way to high-level schedule
status to customers
45. Which of the following is a
key characteristic of an arrow diagram?
a)
Lag
b)
Dummy task
c)
Finish-to-finish dependency
d)
Critical chain
Where are the answers to the questions?
ReplyDeletethank you for sharing the PMP question
ReplyDelete
ReplyDeleteproject management
hi guys visit our blog to know about the project management
PROJECT MANAGEMENT
Hey, If you want to enroll in PMP Certification course then you should click on this link - PMP Certification in India
ReplyDelete