Use the following
information to answer questions one through four below
PV= $2,200
EV= $2,000
AC= $2,500
BAC= $10,000
1. Using earned value analysis, what is the schedule variance
and status of the project described?
a) -$200 and the project is behind
schedule
b) +$200 and the project is ahead of
schedule
c) -$300 and the project is ahead of
schedule
d) +$8,000 and the project is exactly on
schedule
2. What is the CPI for this project and what does it tell us about cost performance thus far?
a) .20; actual costs are exactly as
planned
b) .80; actual costs have exceeded
planned costs
c) .80; actual costs are less than
planned costs
d) 1.25; actual costs have exceeded
planned costs
3. What is the cost variance?
a) +$300
b) -$300
c) +$500
d) -$500
4. Assuming current variances are the typical performance, what is the ECA and what does it represent?
a) $10,000; the original project budget
b) $ 12,500; the original project budget
c) $10,500; the revised estimate for
total project cost (based on performance thus far)
d) $12,500; the revised estimate for
total project cost (based on performance thus far)
5. Life Cycle Cost (LCC) estimates consider:
a) The total life cycle costs of the
project (concept, planning, implementation, and closeout).
b) The differential cost of owning and
operating a system.
c) The total cost of acquisition as well
as operations and maintenance.
d) The total project cost at the time of
customer acceptance.
6. Accelerated depreciation allows a company to write capital expenses off their taxes more quickly. Which of the following is a recognized method of accelerated depreciation?
a) straight line
b) double declining balance
c) rapid capital deduction
d) accumulated cash analysis
7- You have completed one year on the troubled Yucky Mountain nuclear waste disposal project. Numerous concerns have surfaced about the project and you have been directed to perform analysis and recommend either terminating or coniinuing the project' The $2.5 million already spent is referred to by finance experts as -- and expeds contend that these costs should considered in making the decision to continue the project or not.
a) sunk costs; not be
b) allocated costs; not be
c) direct costs; be
d) amortized costs; be
8. The cost of investing in a particular project and therefore giving up the potential benefits of other projects is known as:
a) Variable cost.
b) Fixed cost.
c) Opportunity cost.
d) Indirect cost.
9. Which of the following estimates would most closely predict the actual cost of a project?
a) Order of magnitude
b) Budget
c) Definitive
d) Parametric
10. Which of the following is/are common tool(s) for developing parametric cost estimates?
a) WBS
b) regression analysis
c) content analysis
d) factor analysis
11. Your project is running behind schedule and you decide to crash the network to catch up. Which of the following rules should you follow?
a) Begin noncritical tasks at their
early start times.
b) Use resource leveling to optimize the
productivity of project resources.
c) Crash the tasks that have the longest
duration.
d) Crash critical tasks whose cost of
crashing is lowest.
12. Learning curve theory states that in repetitive production of many items:
a) Production equipment that requires
less operator training results in lower unit costs.
b) Unit costs decrease as production
rates increase.
c) Unit costs decrease in a regular
pattern as more unit are produced.
d) Costs of training increase as the
level of automation increases.
13. Which of the following is not an example of a direct cost?
a) Salary of the project manager
b) Subcontractor expenses
c) Materials used by the project
d) insurance
14. Your project budget was estimated at $2,000,000. The third monthly status report revealed that $500,000 worth of work was complete and that $750,000 had been spent. Your team believes that current variances will not be indicative of remaining performance. What is the EAC?
a) $3,000,000
b) $2,000,000
c) $2,750,000
d) $2,250,000
Using the following
information, answer questions 1s and 16:
Variable costs = $100
per unit
Fixed costs = $2,500
15. What is the cost of producing 20 units?
a) $4,500
b) $2,600
c) $2,500
d) $2,000
16. What is the cost of producing 10 additional units?
a) $25,000
b) b. $2500
c) $1000
d) $600
17. As of the fourth month on the Acme project, cumulative
planned expenditures were $100,000. Actual expenditures totaled $120, 000. How
is the Acme project doing?
a) The project is ahead of schedule
b) The project is in trouble because of
a cost overrun
c) The information available is
insufficient
d) Project costs are within a normal
range
18. Present value is the:
a) after-tax value of working capital
b) value today of future cash flows
c) total budget as of today
d) total budget as of today plus
management reserve
19. Working capital is defined as:
a) current assets less current
liabilities
b) funds reserved for bid and proposal
costs
c) funds set aside for unforeseen
problems
d) the sum of cost plus profit
20. Which of the following tools measures true economic
profit by accounting for the cost of capital?
a) payback period
b) economic value added
c) benefit cost ratio
d) expected present value
21. Which of the following statements about management
reserve is/are true?
i. Management reserve is intended to
reduce the chance of a cost overrun
ii. Management reserve funds may be used to fund work not
originally authorized for the project
iii. Management reserve funds may be
used to fund unforeseen problems
a) I and ii
b) I and iii
c) Ii and iii
d) i, ii, and iii
22. According to the law of diminishing returns:
a) short people are best suited to some
kinds of work
b) using fewer resources will result in
greater profit
c) using more resources will result in
proportionately less and less output
d) using more resources will result in
the project taking less time
23. Which of the following is a cost reduction tool aimed at:
a) analyzing a design, b) determining the necessary functions, and c) assessing
how to provide those functions at the lowest cost without degrading performance
or quality?
a) Pareto diagram
b) Kanban
c) Configuration management
d) Value analysis
24. Which of the following statements are true regarding benefit cost-ratios (BCR)?
I. A BCR greater than zero indicates
a profitable project
ii. A BCR of 2.5 represents a gross
payback of $2.50 for each dollar invested
iii. Benefit-cost ratio represents the average rate of return
on the money invested in a project
a) I
b) ii
c) iii
d) ii and iii
25. Analysis of payback periods determines_________.
a) which project will become profitable most
quickly
b) the future value of money invested
today
c) the ratio of discounted revenues over
discounted costs
d) the first time period in which a
financial profit occurs
26. Also called control accounts, cost accounts are:
a) the lowest level at which organizational
responsibilities are assigned
b) used to summarize project costs at
level two
c) used to identify and track management
reserve
d) usually about two weeks of effort
27. Which statement about bottom-up cost estimating is not
true? The concept
a) identifies cost estimates for WBS
work packages
b) aggregates work package estimates to
yield a cost estimate for the entire project
c) is an example of an order of
magnitude estimate
d) is considered a very accurate form of
definitive estimating
28. IRR is a quantitative measure of a project's expected
profitability and can be thought of as:
a) after tax profit reported to the IRS
b) the average rate of return for the
project
c) the estimate at completion minus the
budget at completion
d) the cost variance percentage
29. Given the following information on the XYZ project, what is the expected outcome? (Assume current variances are typical of future performance)
·
Original
project budget was $400,000
·
The
current BCWP is $200,000
·
The
current BCWS is $180,000
·
The
current ACWP is $250,000
a) The project will finish with a
positive cost variance
b) The estimate to complete is about
$100,000
c) The project will finish with a cost
overrun of $100,000
d) There is insufficient information to
evaluate the project
30. Your project's budget is $500,000. The planned value as
of today's reporting period $300,000, the project is 50% complete and 60% of
the budget has been spent. The earned value for the project is _______ and the
project is _____.
a) $300,000; behind schedule
b) $300,000; on schedule
c) $250,000; ahead of schedule
d) $250,000; behind schedule
31. EAC is a Periodic evaluation of:
a) value of work Performed
b) cost of work completed
c) what it will cost to finish the job
d) estimated total cost at project
completion
32. Analogous estimating:
a) relies on actual historical costs
b) is a form of bottom-up estimating
c) is a form of top-down estimating
d) is used most often during the
implementation phase
33. A CPI of .75 indicates that:
a) you have spent 75% of Your budget
b) you have a cost under run
c) you are over budget
d) your marginal tax is 25%
34. You just completed estimating the cost of a project to renovate an elementary school and install a security and fire-alarm system that meets current city codes. The estimate is $100,000 but experience with data of this type leads you to believe that the actual costs could range anywhere from $90,000 to as much as $125,000. What kind of estimate have you created?
a) order of magnitude estimate
b) budget estimate
c) definitive estimate
d) three-point estimate
35. An order of magnitude estimate would normally be made during which project management phase?
a) initiation
b) planning
c) execution
d) closeout
36. You are in the second month of clinical trials on the development of a new drug which your company is planning to call "Awake". The target market is professional, long-haul drivers and college students who procrastinate on their work. You think things are going pretty well but are about to look at some earned value data to find out for sure. The data show that the CPI is 0.96 and actual costs are $50,000. Given these data, what is the earned value?
a) $48,000
b) $50,000
c) $52,083
d) there is not enough information to
determine the earned value
37. The CPI on the awake project is 0.96 and you have calculated the EAC as $312,500. What was the original budget (BAC) for the project?
a) $325,521
b) $312,500
c) $300,000
d) there is not enough information to
determine the budget at completion
38. You just assumed the PM role for a virtual team with members in six different geographical locations. The project is using earned value analysis and the data for the latest month showed the EV (BCWP) to be $126,000, the PV (BCWS) to be $120,500, the AC (ACWP) to be $130,000, the BAC to be $600,000, and the percent complete to be 0.21. What is the earned value at this point?
a) $600,000
b) $126,000
c) $130,000
d) $120,500
39. Which statement best explains the declining SPI in the graph shown below?
a) The project starter late
b) Insufficient resources are available
to the project team
c) Materials cost less than anticipated
d) A portion of the work was outsourced
40. Most organizations prefer to avoid large changes in spending during any portion of a fiscal year. A technique for reducing such fluctuations is known as ______and is ________.
a) Funding limit reconciliation; a tool
of estimate costs
b) Funding limit reconciliation; a tool
of determine budget
c) Reserve analysis; a tool of estimate
costs
d) Reserve analysis; a tool of determine
budget
Thanks a lot for sharing PMP Certification question.That was a great help
ReplyDeleteGood set of questions related to pmp exam practice again thanks for sharing.
ReplyDeleteThese multiple choice questions are though confusing and also need an amazing IQ level. Got to know about LSAT Courses and perfect strategies taught by them for entrance exams. Schedules of classes are according to the students. Weekly mock tests and daily doubt sessions are in a systematic matter according to syllabus.
ReplyDeleteHey, If you want to enroll in PMP Certification course then you should click on this link - PMP Certification in India
ReplyDelete