Quick Link to Risk Management
Risk Management 11.6 Monitor and Control Risks
Risk Management 11.5 Plan Risk Responses
Risk Management 11.4 Perform Quantitative Risk Analysis
Risk Management 11.3 Perform Qualitative Risk Analysis
Risk Management 11.2 Identify Risks
Risk Management 11.1 Plan Risk Management
Risk response planning is the process of determining how to enhance opportunities or reduce threats. Response planning assigns one or more people as “response owners” and addresses risks according to their priority. Response planning should consider the following factor:
·
The response is appropriate for the severity of
the risk.
·
The response is cost effective and timely.
·
The response is agrees upon and realistic.
·
The response is owned by a specific person
(assigned action item).
Plan Risk Responses
|
||
Inputs
|
Tools
|
Outputs
|
1. Risk
register
2. Risk
management plan
|
1. Strategies
for negative risks or threats
2. Strategies
for positive risks or opportunities
3. Contingent
response strategies
4. Expert
judgment
|
1. Risk
register updates
2. Risk-related
contract decisions
3. Project
management plan updates
4. Project
document updates
|
Two Key Inputs for Plan Risk Responses:
1. Risk Register: Based on the analysis
from the previous processes of identification and analysis, the risk register
provides the following information:
·
Identified risks and priority
·
Root causes and risks grouped by categories
·
List of potential responses
·
Risk owners and risk triggers (symptoms and
warning signs)
·
Risks requiring near term response
·
Watch list of row risks that should be periodically
monitored
2. Risk Management plan: As before, the
risk plan assigns people who own specific risks, defines the thresholds for whether
a risk is low, moderate, or high, and provides the time and budget to conduct
response activities.
Four Key Tools for plan Risk Responses:
1. Strategies for negative risks or threats:
May be addressed with one or more of the following:
·
Avoid:
This strategy attempts to eliminate a threat, if possible. One possible
approach is to adopt an alternative strategy in one of the following ways: 1)
reduce scope or change project objectives, 2) allow the schedule to slip, 3)
adopt a proven technical approach instead of a more innovative, risky one, or
4) use a substitute component that does not have the same risk.
·
Transfer:
PMR suggests that you may consider transferring (deflecting) a risk to another
party through numerous practices:
·
Mitigate:
Actions taken to reduce the probability or the impact of a risk, earlier
preventive approaches are usually more productive than repairing the damage
after it occurs. Conducting more tests or designing back-up systems into
critical subsystems are examples of mitigation.
o
Insurance and performance bonds
o
Warranties and guarantees
o
Outsourcing (also called procurement or
subcontracting)
o
Contract type (a fixed price contract transfers
cost risk to the seller and a cost reimbursement contract transfers cost risk
to the buyer)
Note: Transferring a risk does not
eliminate the risk. It merely gives someone else the responsibility to manage
that risk.
·
Accept:
This approach may be used for negative risks or threats and for positive
opportunities. Passive acceptance is taking no action and dealing with the
problems (or opportunities) if and when they occur. Active acceptance is almost
always handled using extra money, time, or resources (known as contingency
reserve).
2. Strategies for positive risks or
opportunities:
·
Exploit:
This strategy attempts to maximize the chance of reaching an opportunity. lt
uses approaches such as: assigning the most talented resources available,
reducing the time to completion, providing better quality than planned, and
eliminating uncertainty. The sponsor should exert influence where needed.
·
Share:
This strategy involves joint ventures, strategic alliances, and other
collaborative arrangements to share risks, share costs, and take advantage of
technical synergies (each party performs the portion of the project that they
do best).
·
Enhance:
This strategy attempts to increase the "size of an opportunity" by 1)
increasing probability and positive impact (the opposite of mitigating negative
risks) and 2| by identifying and maximizing key drivers of positive
opportunities. For instance, one might decide to leverage the advantages of a
superior technology.
·
Accept:
Used when the organization prefers not to actively pursue an opportunity, but
will take advantage of it if it occurs. For example, the organization might not
wish to divert resources from a more promising opportunity.
3. Contingent response strategies:
Contingent Response Strategy: A response plan that is used only under
predetermined circumstances. This approach is appropriate when planners feel
that future warning symptoms will provide adequate time to implement the
response activity if the conditions begin to occur. For example, a particular
risk response strategy may be triggered only if a specific milestone is missed.
4. Expert Judgment: As always, people with
the right experience, training, and knowledge should be used for the task at
hand (in this case, for response planning).
Four Key Outputs for plan Risk Responses:
1. Risk
Register updates: Again, new information is added to the risk register as a result
of risk response activities. Low risks are put on a watch list. Components of
the risk register at this point include:
·
Identified risks and descriptions
·
Risk owners and response strategies
·
Risk priorities and any probabilistic analysis
that has occurred
·
Risk triggers and the budget/time for
implementing risk activities
·
Contingency reserve that is appropriate for the
organization’s level of risk tolerance
·
Fallback plans ("plan B") for
exceptionally high risks (if the primary response plan fails)
·
Residual and secondary risks (not covered by the
response plan or caused by the response plan)
2. Risk-Related
Contract Decisions: outsourcing is sometimes done as a risk mitigation
strategy.
3. Project
Management plan updates: Elements of the plan that may be updated as a result
of response planning include:
·
Schedule management plan
·
Cost management plan
·
Quality management plan
·
Procurement management plan
·
Human resource management plan
·
Work breakdown structure
·
Schedule baseline
·
Cost performance baseline
4. Project
Document updates: Documents that may be updated include:
·
Assumptions log updates
·
Technical documentation updates
To manage the risk successfully one should have scum in their projects .With high competition, companies have to develop products faster and innovatively always adding value and greater customer satisfaction. In Scrum, it is important to learn and practice its basic principles which collectively and naturally help in the effective management of risk. As a project manager I follow a SBOK guide from http://www.scrumstudy.com
ReplyDelete